Projects Data
HARAM UTILITY SERVICES PROJECT (HUSP), MAKKAH, KSA
1. GENERAL DESCRIPTION | |
---|---|
About the Project
|
|
Location | • Makkah, Saudi Arabia |
Project Type | • Tunnel Sewerage Line Construction |
Final Client (Owner) | • Ministry of Water: National Water Company |
Client (Main Contractor) |
|
Consultants | • SGS: Stucky & Geotest & STUNEX |
Total Tunneling Length |
• 4’479m |
Tunnel Diameter | • 3’510mm (OD) – 2’800 mm (ID) |
Lining |
• Segmental Liningwith integrated HDPE In-Liners. |
Excavation Mode
| • EPB Tunnel Boring Machines (02 No.s.) |
2. SCOPE OF THE PROJECT | |
---|---|
• TBM launching shafts • Tunnels Drives • Segmental Lining • Ground Stabilization • Intermediate Manholes • Receiving shafts • Grouting • Soil Conditioning |
2. SCOPE OF THE PROJECT | |
---|---|
• TBM launching shafts • Tunnels Drives • Segmental Lining • Ground Stabilization • Intermediate Manholes • Receiving shafts • Grouting • Soil Conditioning |
3. STUNEX SCOPE OF WORK | |
---|---|
STUNEX and its partners were providing a Key Consultant Role for this challenging project. Some of our activities included; |
TBM | • Analysis of best Mode for Excavation • Assisted in Procurement of appropriate TBMs • Logistics • Developed Remote Support from Schwanau • Operations Optimization to minimize delays • Maintenance |
Design | • Shafts • Tunnel Lining |
Supervision | • Construction Works • Operations • Geology • Health and Safety aspects • QA and QC as per standards |
Soil Treatment Design | • Soil conditioning during excavation
• Control Water Ingress |
Training of Local Engineers | • Herrenknecht, Germany • On Site by STUNEX staff |
4. CHALLENGES | |
---|---|
Radius
|
• Small Radius Curves (R=80m) |
Geology |
• Difficult Mixed conditions (Rock, Weathered Rock, Soft Soil) • Soil Conditioning design during excavation • Ground Stabilization |
Water |
|
Monitoring |
|
The Haram Utility Services Project (HUSP) is a part of a comprehensive project of developing new sewer system tunnels in Makah. It consists of different parts including the TBM launching shafts, the tunnels, intermediate manholes and the receiving shafts. It is a very challenging project in a dense urban area.
The tunnels are excavated using two EPB TBM’s. Due to the site condition and project requirements, a concrete segmental lining with HDPE inlining has been selected. The project involves several challenges and technical issues including mixed geological conditions, small radius curves and very strict water tightness requirements.
Stunex has been involved in different phases of the project from selection and procurement of the TBM’s to design and site supervision.
Machines: | 2 Herrencknecht EPB 2800, Diamater: 3’510 mm |
Tunnel application: | Sewage |
Tunnel length: | 4’479 m |
Geology: | Mixed condition, rock, weathered rock, soft soil |
Marwa Bahgat | STUNEX, Member of the Board |
Client: | National Water Company of Saudi Arabia |
Contractor: | SBG, Business Group TDRS |
AL HAEER WASTE WATER CONVEYOR PROJECT, RIYADH KSA.
1. GENERAL DESCRIPTION | |
---|---|
About the Project
|
|
Location | • Riyadh, Saudi Arabia |
Project Type | • Sewerage Conveyor Line Construction |
Clients (Contractor) | • Saudi Tumpane – For Project Execution • Abul Jadayel Co. for Contracting and Maintenance – For Tender Study |
Final Client (Owner) |
• Ministry of Water • National Water Company |
Consultants | • ILF (for Supervision) |
Total Tunneling Length |
• 12’000 m
|
Tunnel Diameter | • 3’500 mm OD |
Lining |
• Segmental Lining
|
Excavation Mode
| • Double Shield TBM |
BURAIDAH MAIN SEWER LINE TUNNEL, KSA.
1. GENERAL DESCRIPTION | |
---|---|
About the Project
| |
Location | • Buraydah, Al Qassim Region, Saudi Arabia |
Project Type |
• Main Sewerage Line Construction
|
Clients (Contractor) | • CWC in Dammam • Saudi Tumpane in Riyadh |
Final Client (Owner) | • Ministry of Water • Directorate of Water (Al-Qassim Region) |
Consultants | • Khatib & Alami |
Total Tunneling Length | • 14’800 m |
Tunnel Diameter | • 2’400 mm and 2’600 m |
Lining | • Segmental Lining / Pipe Jacking |
Excavation Mode
| • Tunnel Boring Machine |
2. STUNEX SCOPE OF WORK | |
---|---|
Design | • Tunnel Lining • Comparison between Segments and Pipes Lining • Shafts |
Route of the Tunnel
| • Best Route for the tunnel |
Geological Study |
• Collected the existing info • Study of the borehole already executed • First conclusions |
Site installation
|
• Define the most rational set up to permit an execution in time.
|
Final Client (Owner) | • Ministry of Water • Directorate of Water (Al-Qassim Region) |
Shafts | • Comparison between the different methods • Best method to build the shaft safe and economically |
TBM | • Choice of the mode of excavation • Comparison between Slurry and EPB • Supplier offers study • Logistic design • Mode of mucking |
Soil Treatment
| • Mode of lubrication • TBM launching area • Soil conditioning during excavation |
Cost Estimation |
|
STUNEX provided its assistance for tender analysis and cost estimation of the project when the project was first announced.The estimation was provided as per two variants that are pipe jacking and segmental lining.We also assisted them in choosing the right method for the shaft construction